ICGB PROJECT GAS INTERCONNECTION GREECE-BULGARIA 32” X 182 KM
Client: AVAX
Country: Greece - Bulgaria
Year: 2021 - 2022
Scope: Ø 32” x 182 km
Completed works: Mechanical cleaning, pressure testing, dewatering, Caliper Pig inspection, extra-dry air drying (at dew point) and nitrogen preservation service.
Mechanical cleaning Pressure testing Dewatering Extra-dry air drying Pipeline inertisation Caliper PigTULA-VILLA DE REYES Y RAMAL TAMAZUNCHALE
Client: BONATTI
Country: Mexico
Year: 2020 - 2021
Scope: Ø 36” x 306 km
Completed works: Mechanical cleaning, pressure testing, Caliper Pig inspection, and extra-dry air drying (at dew point).
Mechanical cleaning Pressure testing Extra-dry air drying Caliper PigNPS 48 INCH X 250 KM TRANSMISSION GAS PIPELINE (INTERCONNECTOR) “BORDER OF BULGARIA”
Client: IDC CONSORTIUM
Country: Serbia
Year: 2020
Scope: 250 km x Ø 48” / 402 km x Ø 48”
Completed works: Hydrostatic pressure testing, extra-dry air drying, Caliper Pig evaluating and nitrogen services.
Pressure testing Extra-dry air drying Pipeline inertisation Caliper PigNPS 48 INCH X 42,8 KM BALKAN STREAM BULGARIA SECTION A9 / NPS 48 INCH X 59,61 KM BALKAN STREAM BULGARIA SECTION A9
Client: IDC CONSORTIUM
Country: Bulgaria
Year: 2020
Scope: 102.41 km x NPS Ø 48”
Completed works: Hydrostatic pressure testing, extra-dry air drying and pneumatic testing of stations.
Pressure testing Extra-dry air drying Pneumatic testNPS 48 INCH X 41,7 KM BALKAN STREAM BULGARIA SECTION A4 / NPS 48 INCH X 56,8 KM BALKAN STREAM BULGARIA SECTION A5
Client: BONATTI SPA
Country: Bulgaria
Year: 2020
Scope: 98.5 km x NPS Ø 48”
Completed works: Hydrostatic pressure testing, extra-dry air drying and pneumatic testing of stations and valves.
Pressure testing Extra-dry air drying Pneumatic testNPS 48 INCH X 250 KM TRANSMISSION GAS PIPELINE (INTERCONNECTOR) “BORDER OF BULGARIA – BORDER OF HUNGARY” – SECTION 2, 3, 4
Client: IDC CONSORTIUM
Country: Serbia
Year: 2019 - 2020
Scope: 250 km x NPS Ø 48”
Completed works: Hydrostatic pressure testing, extra-dry air drying, Caliper Pig evaluating and nitrogen services.
Pressure testing Extra-dry air drying Pipeline inertisation Caliper PigTRANS ADRIATIC PIPELINE PROJECT – LOT 2 & 3 48”
Client: BONATTI
Country: Greece
Year: 2018 - 2019
Scope: 366 km x Ø 48”
Completed works: Hydrostatic pressure testing, extra-dry air drying, Caliper Pig evaluating and nitrogen services.