Once the hydrostatic stress and leak testing have finalised, the pipeline is depressurised and emptied.

To undertake pipeline dewatering, we at ITP Service use bi-directional pipeline pigs prior to the filling and calibration operations. The pipeline pig is propelled from the test head receiver up to the initial position in the test head launcher, injecting air as a means of propulsion.

Significant projects

NPS 48 INCH X 250 KM TRANSMISSION GAS PIPELINE (INTERCONNECTOR) “BORDER OF BULGARIA”

Client: IDC CONSORTIUM

Country: Serbia

Year: 2020

Scope: 250 km x Ø 48” / 402 km x Ø 48”

Completed works: Hydrostatic pressure testing, extra-dry air drying, Caliper Pig evaluating and nitrogen services.

Pressure testing Extra-dry air drying Pipeline inertisation Caliper Pig

NPS 48 INCH X 41,7 KM BALKAN STREAM BULGARIA SECTION A4 / NPS 48 INCH X 56,8 KM BALKAN STREAM BULGARIA SECTION A5

Client: BONATTI SPA

Country: Bulgaria

Year: 2020

Scope: 98.5 km x NPS Ø 48”

Completed works: Hydrostatic pressure testing, extra-dry air drying and pneumatic testing of stations and valves.

Pressure testing Extra-dry air drying Pneumatic test

TRANS ADRIATIC PIPELINE PROJECT – LOT 2 & 3 48”

Client: BONATTI

Country: Greece

Year: 2018 - 2019

Scope: 366 km x Ø 48”

Completed works: Hydrostatic pressure testing, extra-dry air drying, Caliper Pig evaluating and nitrogen services.

Pressure testing Extra-dry air drying Pipeline inertisation Caliper Pig